Hi All,

We are developed some customization’s in usr layer.now we want to move all customization’s in ISV layer in the same instance.how can i move these objects?

Regards,

MSDAXS.

Easiest way I can think of:

  1. Make an xpo of changed objects on the USR layer.

  2. Delete them.

  3. Switch to ISV layer (you should have license code for it)

  4. Apply xpo to ISV layer.

Hi Fahd Hamidani ,

Thanks for the given replay.I have small doubt.

is their any way to swithch usr layer to ISV layer without deleting USR objects.

Regards,

MSDAX.

Hi I am also searching for same query, I now its not possible with out deleting usr AS PER MY KNOWLEDGE.

HI santosh.

what will be the possibility if there is no option for export the USR objects and import them in ISV. . like in AOT node->VSproject->DynamicsAxModel Projects doesn’t support Import. it will throw an error.

so - my requirement is - AOT node->VSproject->DynamicsAxModel Projects-> proj1 is in USR- now i want to move the proj1 to ISV…

please help me

Hi Jagaddish,

Please follow the Fahd’s advice, I think it works. ie

Easiest way I can think of:

  1. Make an xpo of changed objects on the USR layer.

  2. Delete them.

  3. Switch to ISV layer (you should have license code for it)

  4. Apply xpo to ISV layer.