Is there a maximum of ressources that can be allocated to a single ressource group?
thank you,
Alex
Hi,
Is there a maximum of ressources that can be allocated to a single ressource group?
thank you,
Alex
Yes and No.
There is no limit to the number of resources you can schedule in a group, there is however a limit of resources the system considers in finite scheduling.
any idea of that maximum?
32 (I think) across the entire route for finite scheduling before AX2012 no idea in AX2012