MAster Planning

In Master Planning if i select a item then the master planning engine will not consider the stock of the underlying items.If i run it blank then its ok.What can be the reason

Hi There are a few settings to check. 1) dimension groups- are you coverage planning by dimensions? 2) if checkmark then you will need to setup coverage plan in item coverage. hope this helps.

Hi, a possible difference between due to your selection is the fact that a dynamic master plan is only created (copy of static master plan) when the plan is runned complete…So if you check the planned orders as a result of the dynamic plan you won’t see a result… Regards, Johan