Master Planning - Planned Transfers

Hi,

Suppose we have enough stock for item X in Warehouse A, but a Sales order is created for X in Warehouse B, which has Zero stock and no POs also. When i run the MRP, System generates Planned PO. Instead, i need System to generate Planned Transfers.

Anything to do with Parameters?

regards

Thomas Philipose

You need to set the item coverage up to tell the system that you do not purchase into B, you use a transfer to reflill it from A and purchase into A.

What AX cannot do is dynamically create a warehouse without a rule, so just because you have it in B it will not randomly look elsewhere - the system needs default rules, so then you would always transfer into B and never purchase into it.