Master planning for items after transactions

Dear all:

Hope you are doing very well.

Is it applicable to run the master planning module with all its functionalists including planned orders after having transactions on items??

Thanks in advance

Yes it is MFA, everything in master planning are suggestions and running it after transactions are done will gave you a realistic perspective of what the next situation of the items will be in the future, you can run it any time depending of your bussiness requirements, but it is generally sugested to be run at least once a week for master planning scheduling, and daily for material requirements planning.

The analysis of master planning should be done previously of transactions to be created/posted (ie. purchase orders, production orders, transfer orders) becouse if you create them and later you realize the transaction was not proper, you will have more work to do to get back to the starting point.