Master Planning - Change to Option to Purchase Requisition

Has anyone encountered the scenario whereby client would like to change planned order to purchase requisition instead of all the other options? This is Dynamics AX2012

Hi Berny,

Did you find the solution to this scenario?

WR

A purchase requisition is not a supply, in planning you have demand and you therefore have a committed supply requirement for internal or external reasons, and therefore a “request” is not necessary. You can stop and report through setting planned orders to approved etc. but you are adding delay into what should be a real requirement for the business to perform (meaning if it was a requisition it should immediately be approved - otherwise you have the wrong people in the planning process)