Hello everybody,
I have an issue with the following scenario:
I have a make-to-order product but some of its components need to be bought using the forecast because I have not enough time to buy the components and produce the final product on time to delivery the sales order.
Is there a way to use the forecast to explode the component requirements of a final product while being unable to firm or produce the planned production order created by this forecast?
Thank you all.
Regards,
Nacho
The two options I’d suggest would be:
Use separate coverage groups for the components versus the finished goods, and then depending on whether you automatically firm/release orders or manually release them, you can separately turn on/off the automation for the groups. This is not a great fit, though, because you’d also want to be able to separate top-level planned orders pegged to “real” requirements versus forecast, and unless you’ve got really good/disciplined forecast and time fence management, this can be a problem.
Alternatively, use two separate master plans. One would be configured to include forecast, the other would not. You then train personnel to view/firm/release component orders generated within the plan that includes the forecast, and to view/firm/release top level orders from the plan that excludes them.
Treat your buy-to-stock elements as buy-to-stock and have them as independent demand. You need to hold stock because of the lead-time and therefore define the minum stock holding to reflect the coverage required for the lead time taking into account average usage and order modifiers etc and then the planning streams go two ways - you never have to firm the forecast, but the explosion through, if triggering the stocking point in the future, will suggest replenishment based upon the forecast requirement.