Please help me out on How production scheduling fuctionality works with “finite capacity” and “infinite Capacity” for work centre or work centre group
Thanks in advance for your time
Anil
Hello,
Please help me out on How production scheduling fuctionality works with “finite capacity” and “infinite Capacity” for work centre or work centre group
Thanks in advance for your time
Anil
If you have 10 hours work and 4 hours capacity for a day infinite will schedule 10 hours today, finite will schedule 4 today, 4 tomorrow and 2 the day after.