Forecast scheduling in Master planning

Hi All,

I believe that forecast scheduling should run purely based on the Purchase/Sales forecasts that we do for the items.

But, for an item I’ve setup the coverage settings to use Min/Max model and i just specified the min & maximum quantities. In this case, system is generating the planned order when i run the “Forecast scheduling”

Is it the usual behavior? If it is, any reasons why it should generate in such way.