Hi,
I am getting the following error while posting of production order Operation Scheduling update process.
I have specified the periods for fiscal year 2010 to 2011.
"Working time StdDay has not been specified for 1/1/2013"
Thanks in Advance
Best regards,
D. Praveen Kumar
The message is quite clear, you are missing working times for 1/1/2013, your production wants to reserve capacity on 1/1/2013 and you don’t have times in your calendar.
In this case, what i should do to resolve the error message? Do i need to ‘Compose working times’ ? or i need to set anything in the routes? kindly provide an explaination.Thank you.
Compose working times, if the times specified on the route are correct.