I have one product pizza, i defined the BOM Line but here i have problem regarding the base bread, we have two type of bread base white and brown, and rest the BOM is same. Can we do this just by defining the 1 BOM or we have to create the two BOM line

thanks

Use the configuration dimension and tie it to the type of bread then set up dimensions and tie to configuration groups in the BOM line. This assumes you know the bread up front. If you do not know the bread at the start two BOM’s or two item numbered do not help you would need to not auto consume and instead manual and set the unused bread to 0. Or edit BOM whilst production order has status created (same as knowing at the start really)