Hi
I have a question about costing, this is the scenario.
-
Create a PO(ex PO00001) and post it.
-
Then the Item came from supplier.
3.Then we sell the Item.
- Then after 2 weeks there a another charges pertaining to the PO00001.
my question is how will the cost be affected to the sales when there another late cost for the PO00001?
Romeo
#2
when the charge invoice is received, you create an invoice and assign it to the purchase receipt entries of your old order.
then you go to financial management==>inventory==>costing==>adjust cost item entries. and run the batch job
then the system will adjust the COGS of your sales entry
kiLL6
#3
Ah…thanks…again ROMEO…ty[Y]