Capacity in WORK CENTER

Thank you for example. I set the capacity at 1 e not 600.

In our plant, before the packaging operation can begin, the semi-finished product that comes out of the oven must be deposited in a silo, that is, a silo that has a capacity of 40 quintals must first be filled. Can I put this silo filling time as a waiting time in the routing line of the product that is packaged?