Capacity costing

Hi All,

I can’t understand how NAV calculate capacity cost per operation for Manufacturing,

I have a situation where I have set setup time 10 min ,run time 20 with a unit cost per =1.15 LCY.

I have a Production Order quantity =5 ,

Before posting Output I can see by the Prod.Order Routing that for this operation I have an Expected Operation Cost Amt.=126.5,then when I post Output with the exactly same setup time and run time I see in Capacity Ledger Entries Direct Cost of the operation 34.5.Why?

I can’t figure it out.

Any help it would be appreciated.

Thanks,

Rigersa