Batch job scheduling

Hi,

How to schedule a batch job to run at the end of every month at 11.59.59 pm ??

Thanks,

Chutti

Hi,

In the batch job dialog in AX 2009, you have a repeat button where you can setup job to run every month (radio buttons in the bottom of the dialog), you can also schedule hour in the top of the repeat button dialog

Hope it helps, please verify solution if it solves your problem

Regards,

Thomas

Hi,

I want the batch job to run on the last day of every month .The number of days in a month differs from month to month so how to specify the frequency of days in the recurrence dialog in batch job ??

Regards,

Chutti

The following link might help you: http://support.microsoft.com/kb/926221

regards,

Thomas