ax2012 rework order

Hi,

I would like to ask how “Rework production order” map in AX?

Let say i have a FG, its BOM line are a raw material and paint. I do not setup any route.

I create a production order and complete the production until ended. FG on hand were update in Ax.

After that, the FG need to be rework with painting? How we going to map it in Ax?

Kindly advice. thanks.

Create a works order with no BOM, add itself into a BOM journal and the paint. Put it in a different production pool/group to identify as rework.

If you have no route there is no indication of the operational rework, but as you have no route and it somehow gets produced it would fall into that process.