i have implemented code to generate invoices based on some condition. when i attached this to batch Job and while the job is running i want to update the progress continuously. how or where can I do this to update the current progress? Thanks for any help
What do you mean by updating progress? If it runs as a batch, there is no UI to show any progress bar or so.
In System Administrator > Inquiries > Bach Jobs > Batch Jobs form
All jobs are listed which are executing. In this form we have Progress column. when i run my batch job i want to calculate and update Progress column. i can only see 100 after the job is completed. i want to update how much percent is done during the execution. Thanks for your reply.
In that case, split your batch job to several tasks. I believe the column shows the percentage of finished tasks, not any progress inside tasks.
Can you help me in Splitting batch job into Several tasks? Thanks
Not really, if you don’t explain what kind of problem you have with it.