about Action message

Hello Experts,

I have a query regarding action message:

After we run the MRP and launch the Requisition Worksheets, i observed that the system has suggested to cancle an exist Purchase order ( qty 38 ) and also generate a new Plan PO with 38 qty.

I have not understood why system suggest to cancle existing one and create new PPO with same quantity,

Thanks in advance for your replay

Anil

Are the dates the same? What are your item coverage settings? (i.e. have you left the default negative days to be 2)

hello AdamRoue,

Thanks for your response.

Yes, the dates are same. we are running MRP applying ‘Regeneration’ Methadogy. And also having negative days setting within.

Hope this will help to understand the query

Anil

Can you post a screen shot of the cancel and new planned order duplication?